Cost Reimbursable Billing
Cost reimbursable billing is based on actual project costs (direct and indirect) incurred up to the billing date within a maximum authorized amount.
Cost reimbursable billing for the federal government sponsorships is conducted in accordance with OMB Circular A110 and applicable agency regulations. Other sponsors may also require cost reimbursable billing.
Cost reimbursable billing in SAP requires a sales order master for the project being billed. The sales order is used to summarize the project costs and produce a bill.
Schedule Billing
Schedule billing is necessary when a sponsor requires MIT to submit a bill for a fixed amount on a periodic basis. This type of billing is not based on actual costs of the project.
Schedule billing in SAP requires a sales contract master for each sponsor being billed. The contract includes important information such as the specific amounts and dates required for billing.
In case of federal sponsors whose projects qualify for the Federal Advance Payment Pool, advance payments may be obtained through the letter of credit business process. While no sponsor billing may be required for these projects, an internal bill is created to record revenues for the projects, based on the Institute’s revenue recognition criteria.
Letter of Credit / Request for an Advance / Cost Reimbursement
Most of the money received for the NASA grants and contracts is by letter of credit. Other methods of receiving money for NASA grants and contracts are by request for an advance and cost reimbursement.